Legislative audit found Ogden's airport lost money every year from 2006 to 2022

The 2024 audit found the city covered $15 million in airport losses from its general fund and Business Depot Ogden fund. The city's fiscal 2025 audit flagged a federal airport grant report filed 15 months late.

Published Mountain Time
Source / event date: OLAG Report 2024-02 (Apr. 2024); FY2025 single audit

Continuing story: Auditing Ogden

Ogden

The Ogden-Hinckley Airport had an operating loss every year from 2006 to 2022, ranging from about $160,000 to $1.7 million, according to an April 2024 report by the Office of the Legislative Auditor General. [1] The city covered the losses "with money from its General Fund or Business Depot Ogden Fund (a total of $15 million)," the auditors wrote. [1]

The report found the city released an airport master plan in 1994 and did not release another until 2020. [1] It said strained relations with Weber County had hindered a tax increment financing agreement that could bring $120 million to the airport. [1] Of $10 million the state provided after a 2020 request, the airport had used $7.6 million. [1] The report made six recommendations. [1]

Utah News Dispatch reported that more than half of the airport's 244 hangars had no inspection on record. [2]

Litigation

The legislative audit did not address issues under litigation between the city and airport hangar owners. [1] In that federal case, Judge David Barlow on Jan. 11, 2022, granted in part and denied in part the city's motion to dismiss. [3]

Grant reporting

The city's fiscal 2025 single audit reports that a required federal financial report for the Airport Improvement Program was submitted "approximately one year and 3 months late (December 8, 2025)." [4] The auditors said staff responsible for the report were not aware of the requirement, and identified no questioned costs. [4]

The fiscal 2020 audit listed a prior-year finding from fiscal 2019 that Airport Improvement Program reports had not been filed, which it reported as resolved. [5]

Recent results

The city's fiscal 2025 report shows the municipal airport lost $282,103 before transfers in fiscal 2025, compared with $1,980,929 in fiscal 2024. [6] In March 2025, the city announced that its redevelopment agency board had approved up to $22 million in tax increment financing for Williams International's expansion at the airport, plus $5.5 million for a waterline. [7]

Sources

  1. Office of the Legislative Auditor General · Report 2024-02, Ogden-Hinckley Airport
  2. Utah News Dispatch · Ogden-Hinckley Airport losing millions, audit finds
  3. U.S. District Court for Utah · Order on motion to dismiss, case 1:21-cv-00075, Jan. 11, 2022
  4. HBME / Ogden City · FY2025 single audit and state compliance report
  5. HBME / Ogden City · FY2020 single audit and state compliance report
  6. Ogden City · FY2025 annual comprehensive financial report
  7. Ogden City · News release on Williams International incentive, Mar. 12, 2025

Reporting by The Utah Ledger from the public records above. AI-assisted, checked against those records.